Michigan B184 Update April 16, 2004

Back to B184 updates * Previous * Next



1) Chamber passing CR test

EMS5A08: (chamber with endplug crack, certified to ~2mbar/day)

Total number of chamber passed CR test:     10

2) Chambers in progress 

EML4A03: Ready for CR test. Hopefully it can be done this weekend.  

EML3C13: Mezz card installed. Will be ready for CR test on next
Monday.

EML3A15: Crate opened and is now sitting on transportation cart.
Needs to be epoxied.

3) Chambers in hospital 

EMS5A02:  

After applying epxoy to the location between tube end and endplugs,
and tested with vecco, we decided to apply epoxy to all tubes. Alan is
doing so today. He is doing wonderfully with the device for applying
epoxy from Curtis and Helmut. This work requires extremely careful work
and is time consuming.

4) Problems and issues to discuss 

- Inplane DAQ system does not work properly. Ed is informed and he is
coming tomorrow. hopefully he will fix the problem soon.

- Chamber logistics: Starting from next week, we may need to transport
chambers to bldg 184. I have discussed with Joerg this noon time and
we both agree to use the platform in bldg 184 as a buffer for chambers
to be moved in and out. This has to be well planned in advance. I
think we neeed to inform Mr. Yves Bernard once every week about how
many chambers, what types and which date to be moved into bldg 184.

- We started to arrange and empty some space for UW team. in any case
we should have and seems can have 6 stations to work with. We feel
it's very important to have 6 stations to work with. considering the
clean room, we can have 7 stations, which is needed since we will have
two students soon.

- We received short M4 screws, 6mm tubing, green valves... thanks Helmut. 

- Housing at CERN We find that it's very difficult to find any rooms
for people who are going to stay longer than one week. particularly
for cheaper ones.

- We are somewhat behind schedule due to dealing with the two EMS5
chambers and many other problems, as i have reported to you.  however,
people are working hard and effectively. we feel we are ramping up. on
the other hand, we think we have past the first phase, which is aiming
at setting up environment, training experts.... now we feel people are
trained and knows how to assume quality, and we are entering a phase
of real mass production.

Zhenngguo Zhao