Michigan B184 Update May 7, 2004 |
Back to B184 updates * Previous * Next
1) Chambers passing CR test Chamber passed CR test this week: EMS5A02, EML4A07, EML4A01 Total number of chamber passed CR test at CERN: 15 2) Chambers in progress EML3A15: Taking CR data. EML3C07: ready for CR data taking. EMS4C16: Top multilayer re-certified. cabling done, T sensors and inplane system tested. HV+SHH cards mounted and tested. Dark current measured. EML3A07: Pressured to 3 bar and leak rate will be measured. Received parts for gluing on the survey target. I am contacting Ed about how to glue the missing parts to be glued on. EMS5C08: Opened crate and started apply epoxy to all tubelets. 3) Chambers in hospital none 4) Other issues: - Space for UW. Half of the planned space for them has been ready. - Joerg discussed with me about filling DB for logistics. I think it's good to do so so that one can track where our chamber will be from internet. I agreed to do so once he opens an account for us. - Two summer students joined us: Pierre Cornell and Ezra Levin. We expect that the production rate to ramp up. Zhenngguo Zhao