Michigan B184 Update May 14, 2004

Back to B184 updates * Previous * Next


1) Chambers passing CR test

  a) Chamber passed CR test this week:  EML3C07
  b) Total number of chamber passed CR test at CERN:   16

2) Chambers in progress 

  EML3A15: CR test for almost two weeks
  EMS4C16: CR test 
  EML3A07: Ready for CR test
  EML4A05: T sensors and inplane system have been tested. Pressure
           recycled and is recertifying the chamber. (one cracked
           tubelet found)
  EMS5C08: Epoxy done, are doing T sensor test and cabling.
  EMS4C10: Epoxy half done 
  EMS5C02: Epoxy half done

3) Chambers in hospital EML4A05

4) Problems 

  a) CR test 

  For chamber EML3A15, we found "hot" channels with large area in the
  same location of the hit map (first half of the hitmap, mostly
  corresponding to mezz card ID with odd numbers. We replaced mezz
  card 1,3,5 and hot channnels stayed. We then measured dark current
  of single tubes for all corresponding hot channels, they are all
  normal.

  This is happenning to EMS4C16 too. and now is happening to EML3C07
  when we use the DAQ system that was used for EML3A15.

  The detailed situation can be discussed at the phone meeting.  

  I myself feel this is not a problem of the chamber itself, but
  something to do with the DAQ system (DAQ system includes trigger in
  my definition). Something must happened to the DAQ system (software
  or hardware?).

  If this problem is not solved in time, we will have to stop moving
  ahead since we have no space to open more chambers.

  Another unfortunate thing is that the two chambers stuck in the CR
  test are the ones I planeed to empty space for UW. I will have to
  deal it urgently next Monday.

  So, strong measures are called for, and definitely needed, to
  overcome the current bottleneck.

  b) Tubelets with crack

  Chamber EML4A05 has worse long leak rate (2.07 mbar/day) for ML2. We
  added the gas to it to 3 bar.  The next morning the pressure had
  dropped to only a few psi, indicating a huge leak. This leak was
  found to be from a tubelet with epoxy.  Appearently the crack was
  further opened up by presurizing the chamber.  A bubbling test
  showed two leaks around the bends (I saw one from top since I was
  holding the tubelet and Reza saw two from side).

  This is probably the most worrysome issue. Let's cross our fingers
  and hope we won't find more. On the other hand, we should pay great
  attention to any chamber with a bad long term leak rate.

  c) On EML3A07 chamber, we found 6 tubes with high dark current. The
  dark current ranges from 100-800 nA at 3.4kV. By applying -HV=2.5 to
  3.2 kV we cured 5 of them. however one tube cannot be cured by
  -HV. It tripped while one increase -HV to 3.2 kV.

  Also the tube with larger resistence found by Rudi (and marked by
  Rudi on the spacer frame) is on this chamber.  So far the dark
  current for this tube is normal (we didn't re-measure the resistence
  before closing FCS, unfortunately. I though about it but then was
  interrupted).
 
5) Other issues   

  a) I wish that any one who takes any parts and tools from blgd 184
  could tell us so that we could register it. Except tracking parts,
  we also want to avoid spending time to search tools which had been
  taken away.

  b) I once more remind that we all to pay attention to safety
  issue. we don't want anyone to be hurt here at CERN, and don't want
  our chambers to be damaged because of our careless. so please remind
  each other while working, walking in blgd 184.


Zhenngguo Zhao