Michigan B184 Update June 2, 2004 |
Back to B184 updates * Previous * Next
1) Chambers passing CR test
a) Chambers passing CR test this week: EMS4C10, EMS4A12
b) Total number of chamber passing CR test at CERN: 24
2) Chambers in progress
EML3C05: Taking data for CR test
EML3C15: Will take CR data this afternoon.
EMS5A10: Survey targets and B sensor platforms glued, cabling done,
T sensors and inplane system tested (one camera has problem and is
not yet fixed). Recertify the chamber.
EMS4C06: Epoxy applied, T sensors, survey targets, B sensor
platforms glued.
3) Problems and other issues,
a) CR test
To speed up CR test, we include the DAQ system set up to
"integration" part. We also started training operators to help do
the mezz card scan once (when?) neccessary.
b) We are close to finishing the preassembly of FC's for all
chambers. We think this is the only way to know how many FC's we
still need. Preassembly of CSM motherboard and mezz cables is
ongoing.
c) We have been requested to fill chamber integration database at
CERN. We will try do do it from next week. Li and I learned from
Stephan how to fill it. This database mainly has chamber location
and integration status.
Zhengguo Zhao