1) Chambers passing CR test

  a) Chambers passing CR test this week: EML3A13, EMS4C06, EMS5C06,
    EML3A05
  b) Total number of chambers passed CR test at CERN:   30

2) Chambers in progress

  EML3A11: CR data analysis
  EMS5A10: This is the chamber which has had all tubes epoxied.  Leak
    rate is around 4-5 mbar/day for helium at 3 bar, reduced about
    half after applying epoxy. MECCA test done. Dark current
    measurement is on on the way.  Three tubes so far have high dark
    current.
  EML3A13: Start dark current measurement
  EMS5A16: Cabling done, survey target and B sensor platform glued.
  EMS4C04: Cabling done, T sensor and inplane system tested, MECCA test
    done.  Start measuring dark current.

3) Chambers in hospital

  EMS5C14: This chamber is similar to EMS5A10.  Leaks were found
    between Al ring and endplug nylon (noryl?) at the rate of 10^-6 -
    10^-5 ml/sec.  Leak rate for top and bottom ML are about 2 and 7
    mbar/day for helium at 3 bar. (top multilayer seems not bad).  I
    think we need to treat this chamber the same as EMS5A10.

4) Problems and other issues,  

  a) Our Vecco He leak detector was broken by a UW student by plugging
    it into 222 V power supply.  A new HV power supply was broken by
    UW team too.

    Yesterday both teams had a joint meeting and we emphasized safety
    (personnel, chamber and equipment safety) issue.  We also announced
    some rules for all to follow.  I'm drafting the proposed rules.

  b) Parts and tools
    Received this week:
    - 64 B sensor platforms
    - SHH and HV cards (not finishing counting yet)
    - 37 type B 1.0m Mezz cables (shipment sheet says type A)
 
Zhengguo Zhao