1) Chambers passing CR test a) Chambers passing CR test this week: EML4C03, EMS5C04 b) Total number of chambers passing CR test at CERN: 35 2) Chambers in progress EML3A09: CR data analysis. EMS4A02: taking CR data. EML4C13: waiting for CR test EMS4A14: installing mezz card EML3C11: testing dark current 3) Chambers in hospital. EMS5C14: Epoxy was applied to the location between AL ring and noryl for all tubes. The chamber cured for 3 days and was then pressurized with Helium to 3 bars. The leak rate is about 7mbar/day for helium at 3 bars. This time epoxy does not improve the leak rate. Q196 didn't find any leaks. We are waiting for the Vecco to scan the leaks once more, and then make decision what to do with it. The Vecco has arrived at CERN, but not yet to bldg184, according to Ed, who keeps tracking on it with the help of Atlas secretary. 4) Problems and other issues a) Mezz card rejection. We have twice mezz card pre-selection, based on mezz card ID and the DB. We probably need to do more round of preselection. The criteria to reject mezz card (HV off and on)from the mezz card scan done by us is still not clear to me. If we stick on the criteria Tieshen gave me (e.g. resolution<3 unit, correlation efficiency > 80 ...) we found many more needs to be rejected. Since mezz scan already gives warning messages. I suggest that in the summary file from the mezz scan to add message indicating which mezz card needs to be rejected due to what reason. Then operators can easily see which card needs to be replaced for what reason. If we don't follow the criteria we have, what do we test. If we strictly follow the criteria, we need to replace many more mezz card, it seems to me. e.g. each chamber I have seen a few mezz cards that have resolution > 3 units (0.78ns/unit). We need to discuss this issue more in detail, and measure needs to be taken to make the criteria clear. b) Mysterious chamber HV trips Many times we find that HV trips during the night. Now we found bugs (insects) are the ones to be blamed, at least we found 2 trips due to bugs. We probably need to find a bug trap to install in bldg184. Anyone know where and what kind of bug trap we should use? c) Chamber transportation We request crane operators to come every morning, and we have good relations with them. So far there have been no problems handling chambers with the crane. But chamber transport has become difficult, at least much slower than before, even though we request the transportation one week in advance. I will discuss this Joerg after his vacation. Zhengguo Zhao