Logo for ATLAS Michigan

Michigan B184 Update July 16, 2004

Back to B184 updates * Previous * Next


1) Chambers passing CR test
 
  a) Chambers passing CR test this week: EMS4A02, EML4C13, EML3A09
  b) Total number of chambers passing CR test at CERN:   38
 
2) Chambers in progress
 
  EML3C11: CR data analysis 
  EMS4A14: mezz card scanning and then take CR data
  EML4C11: waiting for CR test
  EML4C07: waiting for CR test
 
3) Chambers in hospital
 
  EMS5C14: We used Vecco to scan the leaks and found most of the leaks
  improved. we will mark up some tubes with epoxy once more and then
  move this chamber out of hospital since this is the best we can do
  (for the leaks between Al ring and endplugs).
 
 4) Problems and other issues 
   We are now staring another round of inventory. 
   
Zhengguo Zhao

Back to B184 updates * Previous * Next