Logo for ATLAS Michigan

Michigan B184 Update November 19, 2004


Back to B184 updates * Previous * Next

1) Chambers re-working 
 
  a) Total number of chambers need to be reworked: 34
  b) Total number of chambers that have been re-worked: 4

  c) Chambers re-worked this week: EML4A07, EML4C07, EML4A05, EMS4A02,
  EML3C15, EML3A05 
 
2) Chambers in progress

  EMS3A02: Painted epoxy, survey targets and B sensor platform glued  
  EMS3C06: Gas leak certified

  (These 2 chamber are the last 2 EMS3 chambers made in UW) 

3) Problems and other issues
 
  i.  EML1A01 has passed CR test.  The major work to be done for this
  chamber is:

    - measure the long term leak rate
    - test t sensors 
    - mount the mask and test inplane system. 
    - measure dark current
    - modify HV connectors (grounding)
    - replace mezz cards 
    - perform CR test

  However, 8 more T sensors from Boston need to be glued to the
  chamber. UW has the T sensors but they are not calibrated yet.

  ii. EMS3C12 (UW chamber) has over 10 hot tubes. All have been
  treated by -HV and they are no longer hot.  It's very painful to
  deal with hot tubes at the stage of taking CR data since one has to
  open cards and FC to access to the tubes.

  CSM1 and DCS box on this chamber were damaged, according to Jeff.
  No reason was found yet. This chamber was handled by Ried.

  iii. When testing DCS box for one UM chamber, we failed all the
  time. Then Matt was called and he found the low voltage power supply
  was 5.5 V (it should be 5.0 V). In principle no one should not tune
  it and the knobs actually are fix by epoxy. However, Matt touched
  the knob and the voltage went to 10 v. Then Jeff found that 6 mezz
  cards were burned.

  I have informed and emphasized to all people, including UW people, to
  be extremely careful, and strictly follow our rules announced for
  working in bldg184. even though I jumped around 10 chambers working
  in parallel everyday, this still happening.

  iv. EML4C07 has a tube with long maximum drift time. Usually this
  problem is attributed to tubelet blockage. We replaced the tubelets
  at both tube ends and found that the tubelets were fine.  However, 
  the drift time decreased from over 1000 ns to about 860ns, still
  about 100 ns longer than average. The reason of decreasing of the
  drift time might be this time we flushed enough. So it might be that
  the threads on the endplug has blockage, or the tube is
  contaminated.

  This also happened to one UW chamber. 

  v. Otherwise, we are making good progress. We are trying to finish
  UW EMS chambers by the end of this month. This week we should be
  able to finish all UM chambers that need to be re-worked, except the
  33 chambers in bld180, which will be re-worked there intensively for
  about one week.

  Also, as you have seen, we already started re-work UW chambers.

Zhengguo Zhao

Back to B184 updates * Previous * Next