UM chambers:

We are dealing with the two dropped chambers this week. In principle we 
need to re-certify the chambers.

EML4A07
  - leak rate for both ML are around 0.4 mbar/day for Ar+CO2 at 3 bars
  (for over 60 hours).
  - dark current has no problem at 3.4 kV 
  - electronics test is fine 
  - CR data is fine (tdc spectra and charge width)

EML4C07
  - leak rate: still certify, so far looks at the level of 1-2 mar/day
  - dark current is fine

Planned crane operation this afternoon was canceled since the crane team
has to deal with trucks for CMS. 

Next week we will put EML4C07 back to box and perform CR test, and EML4A07
will be mounted to the transportation card.   

The damaged (shape distorted) box for EML4A07 will be repaired by CERN, maybe 
some time next week. 

=========================================================================
UW chambers 

1. Passed CR test: EMS2A04, EMS2A12
2. Chambers in progress

EMS3a08: check leaks

Chamber to be reworked for UW 
EML2C09: Dealing with hot tubes for almost one week. 
EMS3A06: Dealing with hot tubes for almost one week. 
EMS3C16: Taking CR data
EML1C07: Soon be ready for CR test 

===================================================================
1. Problems and other issues

  a) UW chambers that have done CR test at UW appeared to be very
  difficult to work for due to noisy tubes, either hot tube or the
  epoxy applied.  so it is expected that their 44 chambers that need
  to be reworked will take about 3 months if all chambers behavior
  like the two we are working with.

  b) This afternoon there was a demonstration on how to lift chambers
  in bldg180.  Curtis, Matt and I were there (Bing was at another
  meeting). Matt has taken some pictures. My personal feeling is that
  if this is still not safe, hardly we can do anything then. Curtis
  will report the detail, I guess.

Zhengguo Zhao

Back to B184 updates * Previous * Next