Logo for ATLAS Michigan

Michigan B184 Update January 14, 2005


Back to B184 updates * Previous * Next

Definitions of the numbers listed in Summary table:
N(total) = number of chambers to be worked or reworked at CERN in phase I
N(finished) = Number of chamber that have been finished
N(this week) = number of chamber  

1.  Summary table

            N(total)           N(finished)           N(this week)
  UM             80                   79                     0                
  BMC            80                    0                     0
  UW             80                   44                     1

  List of chambers finished this week:  EMS3A08

2.      Chambers in progress

  EIL4C11:  Taking CR data
  EIL4A09:  CR test done
  EIL4C09:  CR test done
  EIL4C13:  Taking CR data
  EIL4A11:  Fixed the leaks in bottom ML and recertified it. 
  EIL4C13:  dealing with high dark current on tube ML1-1-54. 
  EML1A09:  Taking CR data.
  EML2C05:  CR test done. Are testing T sensors and inplane system.  

3.      Problems and other issues

  a) Crane operation.  There has been a safety review and test on
  moving the crane in Bldg180 and Bldg 184 right after the Xmas
  break. This process seems has been finished. The operation in
  Bldg184 formally started since last week. However, the moving of UM
  chambers at Bldg180 is not yet unblocked. I heard that final process
  like signature and documentation was not yet finished. Joerg is
  making effort on this problem.

  Its now not allowed to move two chambers together with the crane. Its
  requested, and we agreed, that US must have one person there when
  moving chambers in Bldg180.

  b) Since EIL4 chambers are special, the determination of the T
  sensors for them has been the bottleneck till yesterday.  Matt is
  now making an effort on this problem and we have to move over this
  step so that these chambers that have past CR test could be moved
  away, otherwise they occupy space and reduce our working efficiency.

  c) Tube ML1-1-54 of EIL4C13 has high dark current, about 0.3 mA at
  3.4kV. Negative HV didn't help getting rid of the high dark
  current. We also cleaned the location between endplug and signal
  cap. The resistance of the wire is normal (~138 Ohms, the same as
  the nearby tubes).  We are still working on this tube. If that is
  still the case, this tube may has to be disconnected.

  d) We are now working with UW chambers, mainly EIL4. a station with
  2 BMC chambers with be set up this Friday. We will start working
  with BMC chambers once Alex arrives at CERN.

  We need to define the working package for BMC chambers. This will be
  done with Alex after we work out 1-2 BMC chambers.
 
  e) Attached is a file drafted by me, and discussed with all senior
  personal who are participating the phase I work and at CERN so
  far. A meeting was held to announce and discuss our task of phase I
  for this year.

  In summary, we have following work to be done at Bldg184 this year

  UM:  
    a) 1 chamber to be moved back to change Mezz card and redo CR test. 
    b) ~25 chambers in Bldg184 need to modify the HV grounding, install
    DCS box (about one week for 2 persons)
    c) Repair EML4A07 chamber (dropped in Bldg180)

  UW: Total 44 chambers to go, including the two H8 chambers that need
    to be apply epoxy and recertify leak rate.

  BMC: Total 80 chambers need to be reworked, including the two H8
    chambers that need to replace tubelets, recertify leak rate. Working
    package for BMC chambers need to be defined.

  We now divided our chambers operators to three groups. On average,
  each group needs to finish 2 chambers per week.

  Also, please tell me who should be added to this e-mail list from each site. 

Zhengguo Zhao

Back to B184 updates * Previous * Next