Michigan B184 Update February 11, 2005


Back to B184 updates * Previous * Next

Definitions of the numbers listed in Summary table:
N(total) = number of chambers to be worked or reworked at CERN in phase I
N(finished) = number of chamber that have been finished
N(this week) = number of chamber finished this week

1.  Summary table
              N(total)           N(finished)           N(this week)
UM             80                   80                          0              
BMC            80                    4                          1
UW             80                   57                          3
-------------------------------------------------------------------
Total         240                  141                          4
                                                                  
2. Chambers finished this week:  

  UW:   EIL4A07, EML2C11, EIL4A13
  BMC:  EMS1A10 

3. Chambers in progress

  UW chamber
    EIL4C05: CR test done, doing cabling and test T sensors and
             inplane system
    EIL4C03: CR test done, doing cabling and test of T sensors and
             inplane ssytem
    EIL4C01: Ready for cr test (DAQ program needs to be modified to
             adapt the special Mezz cable maping, Tieshen and Jeff are
             working on it)
    EIL4A15: Recertifying leak rate of the top ML
    EML1C13: Taking CR data
    EML1A07: Dark current test
    EML1C03: Still waiting for gluing and testing Brandeis T sensors 
         
  BMC chamber      
     EMS1A04:  Taking CR data

  UM chamber

     EML4A07: Continue taking data for trigger panel at the position
              of the middle of the chamber. This afternoon we will
              move the panel to the HV end and take CR data over the
              weekend. By then we will have measurement for three
              positions, i.e. HV and RO ends plus middle.

4.  Problems and other issues

  a) Cabling and testing of T sensor and inplane system becomes a
     bottleneck again and we should try our best to overcome
     it. Otherwise these chambers occupy space and slowdown our speed.
 
  b) The past week and the next week won't reach our planed speed-6
     chambers/week, for the reason:

     - bottleneck from the UW chamber cabling and T sensor testing
     - we have only 2 trigger panels since last weekend (EML4A07 needs
       to be tested for another week)

  c) The four BMC chambers worked out here shown that BMC chambers
     have good quality in terms of test of leak rate, dark current,
     and commisioning the chamber with cosmic rays.

  d) We would like to once more remind both UW and BMC sites to pay
     great attention on the parts. Only you knows your chambers status
     and what parts are missing on your chambers. So please go over
     your record and list and check them.

Zhengguo and David