Michigan B184 Update February 25, 2005


Back to B184 updates * Previous * Next

Definitions of the numbers listed in Summary table:
N(total) = number of chambers to be worked or reworked at CERN in phase I
N(finished) = number of chamber that have been finished
N(this week) = number of chamber finished this week

1.  Summary table

              N(total)           N(finished)           N(this week)

UM             80                   80                          0              
BMC            80                    8                          4
UW             80                   67                          3
-------------------------------------------------------------------
Total         240                  155                          7
                                                                  
2. Chamber finished this week:  

UW:   EML1C01, EIL4A15, EIL4C01
BMC:  EMS1A02, EMS1A04, EMS1A06, EMS1A08

3. Chambers in progress

UW chamber
EML1C05:  Mezz card scan 
EML2C13:  Dark current test
EML1A13:  Dark current test
EML1C09:  Dark current test

EIL4A03:  Tube ML1-3-54 has dark 30-150 nA, leading hot channel in CR data. 
Delt with -HV=3200 V for over night, applied HV=3100 V for three days, replace tubelets. DC stays. We will keep HV=3200 V till sunday or monday, then retake cr data.    

BMC chambers 
EMS1C10: cr test done. will test T sensors and inplane system. 
EMS1C14: flush gas and measure leak rate

UM chamber
EML4A07: Test finished. Chamber is still keep on rotator. 

4. Problems and other issues

  a) Paul and Matt are making great effort to overcome the bottle neck
     from gluing and testing Brandeis T sensors onto EML1
     chambers. Next Monday we may be able to free some stations
     occupied by EML1 chambers.

  b) ETs on BMC chambers are not fully tighten and eventually pretty
     loose.  We retighten them after modifying HV grounding. Three ETs
     have been treated with die (by David) so that they are able to be
     tightened. (no big force is applied for tightening the ETs).

     O-rings on the blind plugs on the ETs are usually damaged. We
     need to replace them.

  c) For EMS1A04, inplane system test for SD, LD failed, possibly due
     to that the lenses were not properly fixed/glued in the right
     position. Informed BMC and Jim looked at them in BLDG184. There
     might be chance in 1.9 to fix them, according to Jim and Matt.

  d) BMC raised concern on how to handle BMC chambers when one has to
     deal with ETs, open FC to access tubes..... A meeting is
     scheduled for this afternoon to discuss how to effectively work
     on BMC chambers.  I have sent my suggested list for discussion.

  e) I attached the check list for working on BMC chambers. The list
     was modified from UM one by Alex and me. If you have any concern
     and suggestions on it, please let us know.

Weekend again, and feels like a short blink. Wish you all a nice weekend,

Zhengguo and David