Definitions of the numbers listed in Summary table:
N(total) = number of chambers to be worked or reworked at CERN in phase I
N(finished) = number of chamber that have been finished
N(this week) = number of chamber finished this week

1.  Summary table
              N(total)      N(finished)      N(this week)
  UM             80                80             0   
  UW             80                80             0         
  BMC            80                22             2
  -------------------------------------------------------------------
  Total         240               182             2
                                                                 
2. Chamber finished this week: 

  BMC:  EIS2C02, EIS2C16

3. Chambers in progress

  BMC chamber
    EIS2A16: One mezz card has a few very hot channels, replaced mezz
             card and redo CR test
    EIS2A14: One noisy channel on one mezz card, replace this mezz
             card and redo CR test
    EIS2A02: flush gas
    EIS2C04: dark current test
    EIS2C10: gas leak measurement
    EIS2C06: grounding HV connectors
    EIS2C08: grounding HV connectors
    EIS2A12: grounding HV connectors
    EIS2C12: gas leak certified and waiting for parts

4. Problems and other issues

  a) We need to figure out how to glue B sensors on the EIL1 chambers.
     Dave, Curtis and I are now looking for solutions.

  b) Matt will make B sensor cables for the B sensor test scheduled
     next Monday.

  c) 10 more BMC chambers arrived in Bldg 184 today.