Michigan B184 Update June 24, 2005 |
Back to B184 updates * Previous * Next
1. Phase 1
We have finished 234 chambers in total, leaving 6 BMC chambers to
go. Of which 5 are expected to have arrrived at CERN by the end of
this month, and the H8 EIS1A08 chamber is ready for CR test (gas
leak certified to ML1=3.3 mbar/day ML2=1.4 mbar/day with Helium for
over 24 hours).
We are keeping EIL2A13/C03 in B184 for T0 study.
UW:
4 BIM chambers that will be attached to EIL4 have been certified
gas leak. Now waiting for HV cards from Italy.
2. Phase 1.9
Following chambers have been finished (4 were done last week)
EML1C05, EML1C11, EML1C13
EML2C05, EML2C11, EML2C13
Zhengguo and David