Michigan B184 Update July 8, 2005


Back to B184 updates * Previous * Next

1. Phase 1

  EIL1AC01, EIL1A03:  finished

  EIL1C09: Doing HV on Mezz card scan. This chamber had no pressure
           when opened. We first measured the leak rate at 3 bar,
           giving a leak rate less than 10 mbar/day.  Then we installed
           the copper tubes and remeasure the leak rate with our DAQ
           system, taking data every 10 minutes. Now the leak rate of
           this chamber appears to be good (a few mbar/day) for over
           40 hours.  So there is no problem for this chamber in terms
           of gas leak).

  EIL2A03, EIL2A11: flushing gas and will measure leak rate over
           weekend.

  Hopefully we can finish the last 3 BMC chambers, and therefore
  finish ALL US chambers for the phase I next week.

  UW:
    Four BIM chambers: still waiting for HV cards from Italy.  
 
2. Phase 1.9 

  Following chambers have been finished
    EML1C15, EML2C01, EIS1A08
 Zhengguo and David